Page 38 - SAMA HSE PLAN
P. 38
Sama Global HSE Plan December 2023
Formwork and Shoring Erection and Removal Plan for Concrete and Masonry Construction and Steel
Erection
Lift Slab Plans for Concrete and Masonry Construction and Steel Erection
Site‐specific Safety and Health Plan for Hazardous, Toxic and Radioactive Waste (HTRW)
Facilities or construction projects holding Resource Conservation and Recovery Act (RCRA)
treatment, storage, and disposal facility (TSDF) permits.
Facilities or construction projects where emergency spill response may be necessary.
Blasting Safety Plan
Delineate provisions for handling, transportation, and storage of explosives; employee training
programs; loading procedures; safety signals; danger area clearance; methods for securing the
site; vibration and damage control; post‐blast inspection and misfire procedures; provisions for
disposal of explosives, blasting agents, and associated material; and post‐blast ventilation
requirements.
Underwater Diving Plan
Plan for Prevention of Alcohol and Drug Abuse
Fall Protection Plan
Steel Erection Plan
Night Operations Lighting Plan for Night Operations of Machinery and Mechanized Equipment
Site Sanitation Plan
Including, at a minimum, provisions for potable water, toilet, waste collection system,
washrooms, showers, and dining facilities
ﻤﯿـــــﺔSﺎﻟAﻟﻌMﺎ اAـــGﻤــLﺳOBAL
11. SAFETY
All Sama Global personnel will be required to:
♦ Participate in Sama Global's HSE Management Process.
♦ Designate a responsible, knowledgeable English speaking supervisor to coordinate safety on site
anytime work is being performed.
♦ Attend and participate in safety meetings, training sessions, etc. to be held as required by Sama Global
HSE.
♦ Proactively participate in safety audits during operations.
♦ Establish lines of communication at all levels so that safe work practices are understood and
implemented.
The purpose of these guidelines is to assist in providing a workplace that protects the safety and health of
the employees of Sama Global. All personnel must conduct their activities in a manner consistent with safe
operating practices, and in conduct with all applicable health, safety and environment (HSE) policies, codes,
and regulations.
The company has an established, written HSE program. The program shall contain our HSE policies and
procedures for implementing project requirements. The program shall address the specific safety hazards of
the work to be performed and shall meet the following minimum criteria and contain the information
indicated.
Revision B For Sama Global Use Only Page 36 of 60