Page 15 - SAMA HSE PLAN
P. 15

Sama Global HSE Plan      December 2023

of the project site HSE program, however, is the responsibility of first line supervision.  The site HSE 
Supervisor reports to the Operations Manager for operational direction and supervision and to HSE Dept for 
functional and technical guidance. 

The HSE Manager conducts periodic onsite reviews of all project operations to assure compliance with client 
and Company safety regulations.  The Manager updates and sets forth interpretations of new or existing HSE 
standards and will maintain a uniform safety and loss prevention program throughout the Company.  The 
Manager also provides assistance to the field staff in all areas related to safety, loss prevention, and health 
and fire protection.   
‫ﻤﯿـــــﺔ‬S‫ﺎﻟ‬A‫ﻟﻌ‬M‫ﺎ ا‬A‫ـــ‬G‫ﻤــ‬L‫ﺳ‬OBAL
The statistics from the monthly project safety reports are compiled for all ongoing projects through the use 
of an electronic data base. The Project Manager and the HSE Supervisor are continually on the alert to the 
overall safety and loss prevention activities of the project by monitoring and analyzing all reports of injuries, 
repairs or damages to equipment and any other unusual safety situations. 

9.3	 Operations	Hazard	Analysis	

Initial Analysis ‐ As soon as sufficient definition of project requirements has been established to make an 
analysis, usually in the preliminary design stage of engineering, an initial analysis is started. A hazard analysis 
will be used as a guideline and represents a listing of general categories of typical tasks, conditions, 
equipment used, materials specified, etc., for which there are special requirements, known hazards or 
special equipment required to perform the work safely. 

The analysis conducted will identify those hazards that will exist on‐site and will indicate preparations to be 
made in order to avoid accidents, injury, work stoppages, delays and other forms of loss.  Any items 
identified in this analysis that may affect the operation of the plant shall be communicated to the owner in 
writing as required by the process safety requirements. 

9.3.1	 Responsibilities	

The analysis is conducted by the project team management, led by the assigned project representative and 
assisted by the Sama Global HSE Supervisor.  Upon completion, the analysis is reviewed by the project 
manager and Sama Global HSE Supervisor, who provide the additional definition necessary to complete 
the analysis. 

9.3.2	 Technique	

Using the guidelines above, the analysis team reviews the planned design, existing plant conditions, 
environmental conditions, erection sequence and the like for potential hazards.  Where changes in design, 
erection sequence, etc., could cost effectively reduce the hazard, these will be incorporated.  Where 
changes are not cost effective, appropriate loss prevention procedures are developed, entered into the 
analysis form and incorporated into the site HSE plan. 

9.3.3	 Follow‐Up	

Follow‐up analyses are needed as the design, planning and execution strategy progresses, particularly if 
significant changes have taken place in the meantime. As a minimum, a review will be initiated by the Sama
Global HSE manager or the site HSE supervisor immediately prior to initial project site activities. Those new 
items identified that have a potential to cause a catastrophic gas release, fire or other major incident within 
an operating facility shall be communicated in writing to the owner. 

Revision B  For Sama Global Use Only  Page 13 of 60
   10   11   12   13   14   15   16   17   18   19   20