Page 21 - SAMA HSE PLAN
P. 21
Sama Global HSE Plan December 2023
♦ Providing fire protection and observing no smoking rules.
♦ Providing fire watch/standby provided where required.
♦ Providing personal protective equipment.
The procedures for permit issuance are specific, areas of accountability are spelled out by the owner or
Sama Global in the site HSE plan, and there shall be no deviations.
9.6.3 Environmental Hazards
Supervisors shall utilize appropriate engineering administrative and personal protective equipment control
measures to reduce or eliminate all identified sources of significant environmental hazards. (Refer to Tables
Appendix A in CFR 1926.55 of the OSHA standards for a listing of hazardous air contaminants and exposure
limits to be met). Workers shall be trained in these procedures as required.
ﻤﯿـــــﺔSﺎﻟAﻟﻌMﺎ اAـــGﻤــLﺳOBAL
The controls measures may be as follows:
Substitute a less hazardous material for one which is harmful to health.
Provide training for employees to supplement existing controls.
Isolate or enclose any process or work operation which may be hazardous.
Use wet methods to reduce the generating of dust; use of local exhaust or dilution ventilation
systems to reduce contaminants getting into the air.
Use special control methods such as shielding, i.e., rotating job assignments so that no employee is
overexposed to any hazard.
Employ personal protective equipment along with protective clothing and respiratory
protection when required.
9.6.4 Fire Prevention/Protection
As with other Sama Global policies, prevention of fires is the goal. Emphasis is placed on preplanning, hot
work permit controls, flammable gas, liquid and material control; the control of smoking; training and use
of warning signs, proper electrical wiring and proper waste storage and removal. Specific procedures are
outlined in the Site Safety & Health Plan.
9.6.5 Housekeeping, Sanitation and Waste Disposal
Good housekeeping is an important part of the HSE program. It is the responsibility of all employees,
including supervisors, to practice good housekeeping. Housekeeping before, during and after an activity is
mandatory to maintain a planned, clean, orderly project site. Worksites, shop areas and all laden areas are
kept clear of scrap and unnecessary materials at the end of each workday. Materials necessary for work are
properly stacked and kept out of roadways to allow proper access for fire fighting equipment. Lay down
areas are planned and laid out in sections with access roadways adequate for fire fighting and materials
handling equipment.
Adequate toilet facilities, cleaning and disposal services and sources of potable water shall be supplied as
required. Subcontractors will provide similar facilities as required by contract.
There shall be compliance with all environmental pollution controls and spills shall be controlled /disposed
according to EPA requirements. Environmental pollution control compliance may include the following:
Do not allow any oils, fuels, paints, solvents, chemicals or contaminated waste waters to migrate
into the plant ditch system or discharge any of this material on the ground.
Revision B For Sama Global Use Only Page 19 of 60